Substation Asbestos Removal, Louvre and Fascia Panel Replacement Project
03 Sep 2010

Balcony Remedial Works to Occupied Residential Appartment Building - Concrete Repairs and Replacement Ballustrades
29 Jul 2010

Transport Depot Internal and External Works: Roofing, Asbestos Removal, Carpentry, Bricklaying
20 May 2010

Torch-On Membrane Replacement with Asbestos Removal Work
20 May 2010

» Replacement of Heritage Deck at Child Care Centre
05 May 2010

Kitchen Refurbishment Complete
13 Feb 2010

Heritage Renovation at Bus Depot Buildings, Tempe
22 Oct 2009

Bandstand Renovation
13 Oct 2009

Bus Depot Works Complete
09 Sep 2009

Routine Building Works Completed Despite Discovery of Asbestos
07 Sep 2009

Retail Outlet Warehouse Campbelltown Re-Roofed
05 Jun 2009



Replacement of Heritage Deck at Child Care Centre


05 May 2010

This project was completed on a building that was built in 1900 as a school. It was vital that the heritage aspects of the building were protected and preserved as works progressed. The building is now used as a day time child care centre.

Scope of Works

- Removal and replacement of existing decking with hardwood timber decking.
- Replacement of structural timber beams.
- Painting of the stairways and handrails
- Lead flashing work


Timing of Works

As the area of work was above the play space of the children, it was necessary to schedule the works for the Christmas holiday close down.

Benefits to Client during Works

- Project was completed in the required timeframe which was critical for all stakeholders.
- No OHS and/or Environmental issues.
- High quality of workmanship with attention to detail in maintaining the heritage fabric.
- No defects on project completion.
- Good communication techniques for the duration of the works with all parties involved.
- Completed project through development & implementation of Site Specific Management Plan.